SFOBB Foundation Removal

Oakland, CA

PROJECT FEATURES

    SFOBB Foundation Removal Phase 1 - E3 Demonstration Project

    • Demolished the largest caisson foundation of the old San Francisco-Oakland Bay Bridge
    • Controlled implosion of below-water concrete structures
    • Efficient bubble curtain design to mitigate noise impacts

    SFOBB Foundation Removal Phase 2 - E4-E18

    • Removal of timber fender system
    • Mechanical demolition of above-water concrete structures
    • Controlled implosion of below-water concrete structures

    SFOBB Foundation Removal Phase 3 - E2, E19-E22

    • Controlled implosion of below-water concrete structures
    • Four bridge piers repurposed into public access structures

AWARDS

    2015 | California Dept. of Transportation | Partnering Success in Motion Award
    2016 | Demolition & Recycling International | World Demolition Award - Collaboration
    2017 | Associated General Contractors | Merit Winner - Marvin M. Black Partnering Award
    2018 | Association of General Contractors of California | Excellence in Partnering Award
    2018 | Demolition & Recycling International | World Demolition Award – Collaboration
    2018 | Demolition & Recycling International | World Demolition Award – Best Overall
    2019 | California Dept. of Transportation | Excellence in Partnering Award
    2019 | Association of General Contractors | Marvin M. Black Partnering Excellence Award

PROJECT PURPOSE

This four-year-long GC/CM project, completed as a joint venture, removed the old San Francisco-Oakland Bay Bridge (SFOBB) foundations. The project was completed in three phases and involved demolishing the foundations using explosives. This project incorporated a high level of collaboration between the SFOBB team and major project stakeholders due to the work's environmentally sensitive and complex nature.